Sope
This document resumes all data generated with the Impact Analysis Report; in order to
produce a clear statement destined to Risk Analysis (Quantitative) assessment and then to give a proper answer the issue’s proposer (see post ). It will be distributed to all concerned parties for either the Change Board or reviewing the existing plans for producing the Exception Report.
In the Risk Governance document (see template) there will be set the threshold value for starting the second phase of this process (see post ).
Quality
The effectiveness can be measured with these parameters:
- Accuracy. All information is linked to its sources
- Clarity. Beside the indication of the actual status, a brief explanation has to be integrated with specific erences (verifying that those documents were updated and accessible to the reader)
- The following checks need to be strictly integrated with the existing documentation both on product and on plan – especially resources (skills, availability, costs).
Document structure
Distribution list
The content of this report shall be made public, being ready to offer all necessary explanations for the decisions taken.
Process description
This document will supply information for creating the Impact Analysis Report. After that, it depends upon the sort of “issue” (e.g. Request for Change or Off Specification – see post ) for the next step. Usually as follows:
- Request for Change will be dealt by the Change Board
- Off-Specification requires some probations possibly in the production process (e.g. Plans), then reviewing test within the Quality (Acceptance Criteria).
RACI (who does what)
| Operation desc./Roles [1] | Spr | PM | BA | SME | TL | Prd | Stkhd |
| Chairing the “Issue & Risk” meeting |
I |
A |
R |
C |
C |
I |
C |
| Asking (formally) for supporting documentation and or technical estimations |
I |
A |
R |
C |
C |
C |
C |
| Chairing the meeting with stakeholders (customers, users, technical people) |
I |
A |
R |
C |
I |
I |
C |
| Analyzing the status of items in order to evaluate the next step (Impact Analysis Register) |
C |
A |
R |
C |
C |
I |
C |
| Describing the result of the completed analysis through the Impact Analysis Report |
I |
A |
R |
I |
I |
I |
I |
| Making decisions about the next step (Change Management or Exception Report[i]) |
C |
A |
R |
I |
C |
I |
C |
Registrar section
These are the key fields
| Impact Analysis ID | ||
| Issue ID | ||
| Issue Type. | RFC/OS (see post) | |
| Issue’s Author | ||
| Stakeholders | People involved in the process | |
| Issue Description | As stated / modified by the author | |
| Priority | To be set (see post about Triage ). | |
| Severity | To be set (based on the available allowances either time or budget) | |
| Status | Working / Pending / Close | |
| Areas involved | Notes | |
| Quality impact: | Reviewing the Test plans-Quality Management Strategy | |
| Other requirements affected: | Prioritization (Kano Model ) | |
| Other tasks affected: | Both from the delivery date and resource allocation | |
| Integration issues: | Listing all components to be reworked and tested as described in the Impact Analysis Report | |
| Life cycle cost issues | The reference is made to the TCO |
|
| Strategical view | Documents required | |
| Involved/Reviewed Benefit: | Business Case and/or Benefits Review Plan[ii] | |
| Involved/Reviewed Risk: | Risk Management Strategy[iii] / Quality strategy | |
| Estimated costs | Measurement Unit | Notes |
| Estimated total effort: | Labor hour / currency | Including LoE |
| Estimated lost effort: | Labor hour / currency | Reworked items |
| Estimated schedule impact: | Delay on delivery date | Within tolerances |
| Additional cost impact: | currency | If any |
| Situation | Resuming what has been assessed in the previous sections | |
| Approved by | ||
Technical domains
- Integrated Master Plan / Schedule
- Stage / Work-package plan
- Product Description
- Quality management strategy
- Risk management strategy
- Resource allocation plans
Financial / Commercial domains
- Business Case (e.g. time to market)
- Cash flow
- Suppliers’ contracts
- Customer’s contract
Notes
References
This page has been produced on the basis supplied by:
www.processimpact.com/process_assets/impact_analysis.doc
[1] Spr Sponsor, PM Project manager, BA Business Analyst, TL Technical Leader, Prd Producer, Stkhd Stakeholder
[i] If the output – impact amount - exceeds the set tolerances, the Exception Report http://www.magnone.eu/prince2-templates/exception-report needs to be more descriptive of the technical and commercial aspects).
[ii] It view notes about Prince2 (new) templates
[iii] It view notes about Prince2 (new) templates